How Pertkelt works
Pertkelt estimates how long a project will take with PERT (Program Evaluation and Review Technique): for every task you give three estimates, and Pertkelt weighs them into an expected time, then adds everything up per section and per project.
A typical project
- 1 Create an organisation (or ask a colleague to add you to theirs).
- 2 As its admin, add the sections your work splits into, and invite members.
- 3 Create a project and add associates: who estimates which section.
- 4 Each associate adds tasks to their section, grouped into sub sections where it helps.
- 5 Drag rows to put them in order or move tasks between sub sections; totals update as you go.
- 6 Download the PDF to share the estimate.
The words Pertkelt uses
- Organisation
- Your team or company. It has members, the sections work is split into, and the projects you estimate. You can belong to several: the switcher at the top shows the one you are working in.
- Members and roles
- Admins run the organisation: they add members, create and edit sections, and edit or delete projects. Users estimate the sections they are assigned to.
- Section
- A kind of work in your organisation, such as Backend, Frontend or Design. Every project is estimated section by section, and each section gets its own total.
- Project
- Something you are estimating. It belongs to one organisation and is split into sections; its total is the sum of all its tasks.
- Associate
- A person assigned to one section of a project: they estimate that section's tasks. A project needs at least one associate per section it covers.
- Sub section
- A group of related tasks inside a section, such as Login or Checkout. Click it to open it; drag tasks into it or out of it.
- Task
- One piece of work, estimated three times in hours: optimistic, realistic and pessimistic.
- Optimistic, realistic, pessimistic
- Optimistic: if everything goes right. Realistic: the most likely case. Pessimistic: if things go wrong, short of a disaster.
- Expected time
- PERT's weighted average: (optimistic + 4 × realistic + pessimistic) ÷ 6. It stays close to the realistic value but allows for risk.
- Quick calculation
- An estimate without an account: just tasks, no organisation. It stays with this browser session; sign in to keep projects for good.
An example
A task you think takes 2 hours at best, 4 most likely and 12 if things go wrong: (2 + 4 × 4 + 12) ÷ 6 = 5 hours expected.
Step by step, with screenshots
Public Calculator
To get started, name your project and add as many tasks as needed with appropriate time estimates for each. For example, it can look like this:
Here are some tips to help you get better estimates:
-
Break down the project into smaller tasks: Breaking the project into smaller, more manageable tasks will help you understand its scope and the amount of time needed to complete each task.
-
Use historical data: If you have completed similar projects in the past, use data from those projects to estimate the time needed for the current project.
-
Involve team members: Team members can provide valuable input on the time needed to complete specific tasks, so involve them in the estimation process.
-
Use optimistic, pessimistic, and realistic estimates: Use optimistic, pessimistic, and realistic estimates to create a range of possible outcomes. This will help you plan for potential delays or unforeseen circumstances.
Once you have added all your tasks, click on "Calculate". The result will show you the estimated time needed to complete the project.
From there, you can add or delete tasks, or adjust their time estimates as needed in sidebar form. You can also click on "Download PDF" to save the estimate to your device. This is the only way to save estimates as an unregistered user.
Registered Users.
So, you want to add more team members to estimates and save your projects for later referencing for future estimates? Say no more. Register (If you do't pick an avatar, an awesome Panda will be assigned to you), and then follow these steps.
- Create an organisation, you will have easy link once you log in.
- Your organisation dashboard will look something like this, from here you can add more users, define sections inside your organisation and create projects for estimation:

- Let's first add a new user:

That user will be added to the organisation, and if they already don't have an account, will be sent a URL to their email to setup their account. Simple for them right? - Go to sections part in your dashboard and create a section, for example we have this:

- Only thing left is to create a project. Pick a name and add people for estimation. Each project can have multiple sections and each section can have multiple people making estimates for it. Each user that is added will receive an invite on their email for estimation.

- Users can now estimate, they can define further sub sections for easier distribution of tasks into meaningful units. All tips for public estimates also apply here. Tasks can also be left on their own. All tasks inside sections and sub sections are sortable between themselves, just drag and drop. Tasks can also be dragged out and into sub sections with ease.

- Once the estimates are done, PDF file can also be downloaded with ease. Button is located at the bottom of the page